DP World brings its Fujairah terminal in the UAE forward to 2028

DP WORLD

Cheaper to insure than a Hormuz transit, but your boxes still cross the UAE overland.

What a Fujairah call removes from a liner rotation, what stays with it, and why the date the strait reopens matters more than the new opening date.

Portside Report·13 Nov 2026·3 min
Executive summary

DP World has moved the opening of its Fujairah terminals in the UAE forward to 2028. A call there avoids the Strait of Hormuz, which makes it cheaper to insure. The coast is still in the war-risk zone, and cargo still has to cross the country by land. If the strait reopens first, Fujairah is likely to serve as a backup berth.

DP World has brought forward the opening of its planned container terminals at Fujairah, on the United Arab Emirates' east coast, outside the Strait of Hormuz. The strait has been effectively closed to container shipping since the first week of March. The first phase is now targeted 18 to 24 months out. In July, when the deal was announced, the estimate was 24 to 30 months. That puts the opening in 2028.

For a liner planner, Fujairah is a UAE call with no strait transit in it. Underwriters still quote it for war risk. The Joint War Committee's latest circular, dated 29 July, names the United Arab Emirates, including its ports and the water out to 12 nautical miles. The Gulf of Oman is listed as well. So the charter's war clause still applies to a Fujairah call.

The difference is the price. In the first days of the war, Lloyd's List put war-risk cover for a Hormuz transit at roughly 1.5% to 3% of hull value. A Fujairah call was quoted at 0.3% to 0.5%. Those are March figures, and the market has moved since. The call buys that gap, on every voyage.

The road stays too. Jebel Ali, DP World's main UAE port, has stayed open through the crisis, but the ships stopped coming. So cargo lands at east-coast quays that DP World does not run. From there it crosses the country by road and rail to Jebel Ali, about 3,500 TEU a day. The new terminal, at Al Rugaylat near Fujairah airport, gives DP World its own berth. It replaces the sea leg into Jebel Ali. The land leg is still there.

That land leg sets the terminal's limit. At 3,500 TEU a day, the land flow comes to about 1.3 million TEU a year. Al Rugaylat is planned at 2.5 million. A terminal that size feeding the same free zone would need roughly twice today's land flow, and trucks alone will not carry that. It needs rail.

This is why the strait's reopening date matters more than the terminal's opening date. Carriers have told DP World that Jebel Ali services could resume within one to three months of safe passage. If that happens before 2028, most mainline ships go back inside the Gulf. Fujairah then becomes an Indian Ocean call and a standby berth for the next closure.

DP World has planned for that outcome. It builds in phases "according to demand", so it can stop after the first. The 2028 date also rests on an agreement in principle, and in mid-October Gulf News reported that construction had not started.

Watch the first carrier to publish Al Rugaylat as a fixed call, and check whether that call replaces Jebel Ali in the rotation or sits next to it. If it sits next to Jebel Ali, Fujairah is the standby berth.

Primary sources

Keep reading

All articles →

Portside Report, by email.

What each development changes on the quay, on board and in the schedule. Free to read. No paywall.

Weekly. One click to leave. Privacy