India approves a second container terminal at Kamarajar Port

_

When can you actually write the new berth into a rotation?

Kamarajar's mainline calls still share one 400-metre berth, and the quay for 24,000 TEU ships opens two years after a concession award that has not happened yet.

Portside Report·27 Nov 2026·3 min
Executive summary

India has approved a second container terminal at Kamarajar Port, near Chennai, built for ultra-large ships. Today the port's mainline calls share one berth that is nearly full. A second berth exists only once the new quay is built, two years after the contract award, so the award date decides when any line can schedule it.

India's cabinet approved a second container terminal at Kamarajar Port on 25 November. It will cost ₹4,288 crore, about $463m. Kamarajar, formerly Ennore Port, sits about 24 km north of Chennai on India's east coast. The new quay is designed for ships of up to 24,346 TEU and 400 metres. Today every mainline call at the port shares one berth, and that berth ran at 88% in 2025-26.

The port's water is already deeper than its berth. In July the port finished a dredging project and now offers an 18-metre operational draft. Its only container terminal, Adani Ennore Container Terminal, has 15 metres. Its quay is 400 metres long and works one mother vessel at a time. When two arrive together, one waits at anchor. At 88% there is little slack to absorb a late ship.

The new terminal is designed to close that gap. Its design draft is 18 metres, the same as the channel. Phase 1 builds 500 metres of quay for 1.1 million TEU a year. That is room for one 400-metre ship and its mooring lines, so phase 1 gives the port its second mother-vessel berth.

So when can a line put that berth into a rotation? Commercial operations start in month 25 after the concession award, and there is no award yet. A private operator will build, finance and run the terminal for 40 years. The tender went out in August, and bids are now due in December. In June the plan was an award in February 2027, with construction from about August 2027. If both dates hold, phase 1 gets around 18 months of actual building. That has to cover 500 metres of piled quay, its yard and its cranes.

The port's first terminal is the benchmark. Its concession was signed in March 2014. Phase 1 was commissioned in October 2017, three and a half years later. The new plan asks for the same step in about two years. Some of the job is already done, because the channel is deeper and the port hands over the land as it stands.

A planner only writes a call into a pro forma once he believes the commissioning date. That takes a named concessionaire and piles in the ground. The date to watch is the award. Compare it with the February 2027 the port planned in June. The 24 months only start counting from the award, so any slip there moves the second berth back too. Until then, Kamarajar's mainline calls keep sharing one berth.

Primary sources

Keep reading

All articles →

Portside Report, by email.

What each development changes on the quay, on board and in the schedule. Free to read. No paywall.

Weekly. One click to leave. Privacy