DP World raises spend on Mozambique's Maputo terminal to $200m

Meeting Chairman and President Chapo
Meeting Chairman and President Chapo

When can a 14,000 TEU ship actually call at Maputo?

The quay doubles in mid-2027 and the deeper channel follows a few months later. The 650,000 TEU figure rests on yard work nobody has itemised.

Portside Report·19 Nov 2026·3 min
Executive summary

DP World will spend $200m on its container terminal in Maputo, Mozambique, and now targets 650,000 TEU a year by mid-2027. The quay more than doubles, with room for two ships at once, so lines get firmer berth windows first. Bigger ships follow once the port's channel is dredged, and the full figure also leans on yard and rail work.

DP World is raising its investment in the container terminal at Maputo, Mozambique's capital and largest port, from $165m to $200m. It now targets 650,000 TEU a year by the second quarter of 2027. When construction started in May 2025, the target was 530,000 TEU. The quay more than doubles, from 308 m to 650 m, which is long enough for two ships at once.

The bigger ships come later, because the berth and the channel finish on different dates. Depth alongside goes from 12 m to 16 m in mid-2027. From then on, the limit is the approach channel at 14.4 m. The port's concessionaire, Maputo Port Development Company, launched a $150m project on 12 October to dredge it to 15.3 m. DP World is one of its shareholders. The work is planned to take about 12 months. If it holds that schedule, the 14,000 TEU class the channel was designed for can come in around October 2027.

So in mid-2027 lines get a second berth, and the depth follows. The second berth matters more than it sounds. On one berth, a ship that misses its window takes the next ship's window with it. Most loops calling Maputo carry on up the coast to Beira or Nacala, so the delay travels with them. With two berths, the terminal can promise a fixed weekly window and keep it when the ship before runs late.

Keeping that promise depends on the cranes. Two ships alongside will share three new ship-to-shore cranes plus whatever mobile harbour cranes stay on the quay. At 650,000 TEU a year, that is 12,500 TEU a week. A big exchange on one vessel leaves less crane time for the other, and the berth planner makes that split every day.

The crane count is also the reason to look twice at the 650,000 figure. The extra $35m comes with 120,000 TEU of extra target capacity. Quay length, depth and crane count are the same in every account of the plan. None of the coverage says what the extra money buys. That leaves the yard, the gantry fleet or a higher productivity assumption to carry the difference. No line has announced a 14,000 TEU deployment to Maputo either.

The berth gain is the part that can be checked first. Maputo ranked 273rd of 400 in the 2025 edition of the World Bank's Container Port Performance Index. The next edition will show whether the second berth cuts time in port.