Durban port delays force Metair to fly car parts in

Image: AutoZone
Image: AutoZone

A parts buffer built for a three-day wait runs out at eight

How a queue at the terminal that brings parts in became airfreight, overtime and one stopped line, and what would carry it on to vehicle exports.

Portside Report·18 Nov 2026·3 min
Executive summary

Ships now wait more than a week to berth at Durban, South Africa's main container port, after a software change slowed the terminal. Car parts arrive on those ships, so one supplier is flying parts in and a customer line was briefly stopped. Cars leave from a different terminal, so exports are at risk only if the plants stop.

Metair, a South African parts maker that supplies Volkswagen, Ford and Toyota, said on 13 November that port delays approaching 20 days had forced it into airfreight and overtime. One production line at a customer was briefly stopped. The delays are at Durban Gateway Terminal in Durban, which handles about half of South Africa's container freight. Container handling there collapsed after a software change in mid-August. The question now is whether one supplier's problem spreads to the vehicle plants.

The cars leave from a different terminal. Transnet's car terminals handled a record 910,424 vehicles in the year to March 2026, and 52% of them were exports. Nothing in the current coverage shows car carriers waiting at Durban. Exports are exposed in one way only. A plant that cannot build has no cars for the booked sailing.

That puts the container queue at the centre of the story, and the terminal sets its length. In early August ships spent around 116 hours alongside. That came on top of 166 hours at anchor. A ship that holds the quay for nearly five days keeps the next one waiting for nearly five days. The cranes, the yard equipment and the system decide that rate. A cargo owner controls none of them.

Once the box is offshore, the consignee has nothing left to pull. The ships carry mixed cargo, so car parts cannot be brought in first. A plant's buffer is sized to how long the pipeline normally takes and how much that varies. The previous operator's best wait was about three days. On 2 October South Africa's transport minister put the average at 8.3 days. A buffer built for the first number runs out on the second. A planner can stock for a delay he knows about, but not for one that moves every week.

So companies pay to get around the queue. Some truck goods from Gqeberha (formerly Port Elizabeth) to Gauteng, the Johannesburg and Pretoria industrial region. Metair has been flying parts in since August. Airfreight works for small, valuable parts. It cannot carry everything. When it falls short, the line stops. Metair described exactly that order: airfreight, then overtime, then a stoppage. It does not expect meaningful improvement before the end of the first quarter of 2027.

The number to watch is the terminal's average anchorage wait, week on week, against the 8.3 days of early October. The figures in circulation mix averages with worst cases, so compare averages only. If the average falls through December, the queue is unwinding.